YONGE EGLINTON CENTRE

POWER FEEDER REPLACEMENT

Project Analysis

McGregor Allsop successfully completed the Design, Tendering, Project Administration, and Commissioning to replace the existing emergency Power feeders to buildings existing Fire Pumps.

New ULC Listed Controllers

Our Approach

The scope of work included the new dedicated feeders, protection, and controllers with transfer switches for four (4) 150HP Fire Pumps in high-rise buildings. New MI cables, fire-rated for 2 hours, were constructed in two (2) high-rise towers from the rooftop generators to the basement Fire Protection rooms.

New feeders were constructed from two (2) Utility substations to Fire Pump Controllers. New breakers with solid-state protective relays were installed to protect new feeders and new Fire Pump controllers. All construction tasks were completed and commissioned within 12 months with no major interruptions to normal operations of the facilities.

More Images

Owner: RioCAN YEC Holdings Inc.

Completion Date: 2023

Project Type: Emergency Power Feeder Upgrade to existing Fire Pumps

Related Projects

TMU, JORGENSON HALL

GENERATOR REPLACEMENT

TORONTO WESTERN HOSPITAL

AIR HANDLING UNITS REPLACEMENT

LAWRENCE ALLEN CENTRE

FIRE ALARM SYSTEM REPLACEMENT

REACH OUT TO OUR EXPERTS.